The weather has made a slight impact.  Work was halted for six snow days thus far.  The project schedule allowed float for five snow days, so one day will need to be made up.  The construction team is confident that it will not be a problem to work extra hours to make up the lost time.  Once the weather is better, they will start ten hour days, plus Saturdays.  Work time will be from 7AM to 5PM, as set by the town.

The steel is going up as planned.  Soon the building will be wrapped.  This will allow the building to be temporarily heated for indoor work, such as pouring the concrete for the floors, to begin.

Angier has been designed to have solar panels on the roof.